34 4th St, Elizabeth, NJ 07206

Great opportunity in Elizabeth, NJ.

This Westville home consists of 4 beds, 2 bath, 1,400 sq. ft. of living space on a 1,376 sq. ft. lot. Don’t miss out on this great opportunity!

Investment and Property Details

Explore our current deals and join us in transforming properties into profitable ventures.

As-is Value:

$250,000

After Repair Value:

$450,000

Investment Duration:

48 Days (44–day renovation phase and a 4-day final closing period)

Return on Investment:

50% ROI

Rehab Cost

$84,000

End Buyer Agreed Purchase Price:

$432,000


Security

IMPORTANT NOTICE: Investment Security and Closing Guarantee
A Purchase Agreement has been signed with a committed End Buyer, providing an anticipated exit for the project.

In the event the End Buyer fails to close immediately following the property rehab completion, Strandpark Properties Limited is contractually obligated to pay the investor their full Return on Investment and Initial Investment on the exact date agreed upon by the investor and Strandpark Properties, as stipulated in the Joint Venture Contract Agreement. This serves as a principal guarantee and ensures the investor is paid on schedule regardless of the final sale timeline.

No Additional Capital Calls: The Operating Partner is solely responsible for any cost overruns, protecting the investor from being asked for further funds beyond the initial $84,000 commitment.

Information Rights: Weekly financial reporting requirements ensure complete transparency, allowing the investor to monitor the project’s financial health in real-time.

Lead Contractor

Joe Smith


Rehab ItemBudget
Kitchen renovation$12,000
2 bathroom renovations$10,000
Electrical$8,000
Plumbing$7,000
HVAC/heating$7,000
Flooring$6,000
Drywall & interior repairs$6,000
Interior painting$7,000
Windows, doors & trim$5,000
Exterior repairs$5,000
Fixtures & lighting$3,000
Cleanup & dumpster$2,000
Contingency$6,000
Total$84,000

44-Day Renovation Schedule

PhaseTimelineBudget
Demolition & cleanupDays 1-5$5,000
Electrical & plumbingDays 6-14$15,000
HVAC/heatingDays 10-16$7,000
Kitchen renovationDays 15-25$12,000
Bathroom renovationsDays 18-28$10,000
Drywall & interior repairsDays 24-31$6,000
FlooringDays 29-34$6,000
Interior paintingDays 32-37$7,000
Windows, doors & trimDays 34-39$5,000
Exterior repairsDays 35-40$3,000
Fixtures & lightingDays 38-41$3,000
Final punch list & cleaningDays 42-44$2,000
Total Renovation44 days$81,000
Contingency$3,000
Total44 days$84,000

Closing

Days 45–48: Final walkthrough, closing preparation, title/closing coordination and sale to the end buyer.

So the complete project timeline would be 48 days: 44 days renovation + 4 days closing.

COMPS

$429,000 — 4/2 — September 11 2026

$760,000 — 4/2 — June 11 2026

$470,000 — 4/2 — July 21 2026

$400,000 — 3/2 — June 18 2026